COVID-19 related construction disputes remain a significant part of modern Construction & Projects Disputes because the pandemic exposed how vulnerable large scale projects are to sudden disruption of labour, materials, logistics and regulatory environments. Even as sites have returned to normal operations, parties continue to argue about who should carry the time and cost consequences of lockdowns, supply chain disruptions, quarantine rules and emergency legislation. Understanding how pandemic events intersect with force majeure, change in law, extension of time mechanisms and risk allocation is essential for employers, contractors, subcontractors and lenders who are still dealing with legacy claims or re-evaluating contract structures for future crises.

How COVID-19 Disrupted Construction Projects

COVID-19 affected construction in multiple, overlapping ways. Government lockdowns halted or restricted site activities, cross border supply routes were disrupted, factories closed or reduced output, and workforce availability dropped due to health restrictions, travel bans and social distancing measures. Projects suffered delayed material deliveries, reduced productivity, resequencing of works and extended preliminaries. Financing pressure, shifting employer priorities and uncertainty about future demand led to scope adjustments and in some cases suspension or termination of projects altogether.

Common Categories of COVID-19 Construction Claims

Most pandemic related disputes fall into a number of recurring categories, each involving detailed contractual interpretation and factual analysis.

Force Majeure and Exceptional Events

Many parties notified force majeure relying on epidemic, government action or general exceptional event wording. Disputes arose over whether COVID-19 and related measures fell within the clause, whether performance was prevented or merely hindered, and whether notice requirements were strictly followed. Tribunals often focus on the precise contract language, timing of notices, the specific government measures in place and the extent to which the contractor could reasonably mitigate disruption.

Extensions of Time and Liquidated Damages

Contractors commonly sought extensions of time for delays caused by site closure, social distancing protocols, supplier shutdowns and quarantined staff. Employers assessed whether these events were designated employer risk or contractor risk under the contract. Where extensions were granted, disputes still emerged about concurrent delays, whether the critical path was truly affected and whether liquidated damages should be reduced or entirely waived for COVID-19 periods.

Prolongation and Additional Cost Claims

Beyond time relief, many contractors pursued recovery of prolongation costs, idle resources, increased logistics expenses and productivity losses. Success depends heavily on contract wording about entitlement to cost for force majeure or change in law, as well as the quality of cost and productivity records. Employers often challenge these claims on the basis that the contract allocates the financial risk of force majeure to the contractor or that the evidence does not sufficiently isolate COVID-19 impacts from other inefficiencies.

Change in Law and Regulatory Measures

Some contracts contain change in law provisions that entitle contractors to time and cost adjustments for new or amended legislation. COVID-19 prompted emergency regulations, health and safety directives and worksite capacity limits. Disputes focus on whether these measures qualify as changes in law, from what date they apply, and whether they impose additional cost beyond what the contractor was already expected to bear as part of ordinary health and safety compliance.

Suspension, Termination and Demobilisation

During the pandemic, employers and contractors considered suspension or termination due to economic uncertainty or prolonged disruption. Disputes arose over whether suspensions were contractually justified, what compensation applied for demobilisation and remobilisation, and whether terminations were lawful or constituted repudiatory breach. These cases require close examination of suspension and termination clauses, notice sequences and the proportionality of the decision in light of evolving COVID-19 restrictions.

Evidence and Causation Challenges

COVID-19 disputes are particularly challenging from an evidential perspective because delays and cost overruns often had multiple causes. To succeed, parties must show that pandemic related events, rather than pre existing issues, drove critical path delay or specific cost increases. This requires robust project records, including contemporaneous programmes, daily reports, material delivery logs, workforce attendance records, health and safety directives and financial data. Delay experts and quantum experts play a key role in separating COVID-19 impacts from other project inefficiencies or employer driven changes.

Contract Drafting Lessons from the Pandemic

The experience of COVID-19 has led many employers and contractors to revisit standard forms and bespoke agreements. Clauses addressing force majeure, exceptional events, change in law, pandemics, remote working, health requirements and digital processes are being drafted with greater precision. Parties are more explicit about whether time and cost relief is available, how notice mechanisms operate, what documentation is required and how long term suspensions should be handled. Clear risk allocation around epidemics and government responses reduces uncertainty and makes future disputes easier to manage.

Dispute Resolution Pathways

COVID-19 related construction disputes have been addressed through negotiation, contract based dispute boards, adjudication, mediation, arbitration and court proceedings. Many parties chose structured negotiation or mediation to avoid the cost and delay of fully contested proceedings, particularly where relationships were long term or projects remained ongoing. In higher value or more complex cases, arbitration has been the preferred forum because of its flexibility, confidentiality and access to specialist construction tribunals.

Ongoing and Future Impact

Although the peak disruption period has passed, COVID-19 disputes continue to surface in final account negotiations, post completion defect claims and lender discussions. The pandemic has also shaped broader risk management practices, encouraging parties to invest more in supply chain resilience, local sourcing, modular methods, digital project controls and proactive scenario planning. Lessons learned from COVID-19 now influence how parties model risk for future shocks, including geopolitical events, climate related disruptions and new public health crises.

Conclusion

COVID-19 related construction disputes illustrate how quickly external shocks can stress test contractual structures, project governance and risk allocation in Construction and Projects Disputes. By analysing how force majeure, change in law, extension of time and cost entitlement operated under real world pressure, employers and contractors can refine their contracts and project controls for the future. Strong records, disciplined notice procedures and pragmatic dispute resolution strategies remain essential to managing legacy COVID-19 claims and to preparing for the next major disruption to the construction industry.

Need to know more? Better ask Handle