Delay analysis and expert evidence sit at the heart of complex construction disputes, particularly within the wider context of Construction & Projects Disputes, where project completion dates, critical path activities, and liquidated damages often determine the financial outcome of a case. Large infrastructure, energy, and real estate developments rely on detailed programmes and sophisticated planning tools. When projects overrun, parties turn to delay experts to explain what happened, who is responsible, and how much time and money is at stake. Understanding the role of delay analysis and expert testimony is therefore essential for employers, contractors, and subcontractors involved in high value disputes.

The Purpose of Delay Analysis in Construction Disputes

Delay analysis is the process of examining project records and programmes to determine the cause, extent, and impact of events that affected completion. Its main objectives are to identify which activities drove the critical path, to allocate responsibility for delay events, and to quantify entitlement to extensions of time or exposure to liquidated damages. Because most construction contracts link delay to financial consequences, a well structured analysis frequently becomes the central evidential foundation in arbitration or litigation.

Common Delay Analysis Methodologies

Tribunals and experts recognise several established methodologies. The choice of method depends on the quality of project records, the nature of the delays, and the requirements of the governing contract or protocol.

As Planned vs As Built

This method compares the original baseline programme with the actual progress achieved. It can be useful where changes are limited and records are strong, but it is often criticised for oversimplifying complex delay interactions and failing to reflect contemporaneous expectations during the project.

Impacted As Planned

Under this approach, delay events are inserted into the original programme to assess how they would have affected completion had the project unfolded exactly as planned. While conceptually straightforward, it often departs from reality because it does not fully incorporate subsequent changes or out of sequence working.

Time Impact Analysis

Time impact analysis relies on contemporaneous programme updates. Each delay event is modelled in the relevant update to see how it changed the forecast completion date. This method aligns more closely with how the project was actually managed and is widely favoured where regular updates exist.

Window or Period Analysis

Window analysis divides the project duration into time periods or windows and examines what caused delay within each period by comparing planned and actual progress. It is particularly useful where multiple delay events overlap or where the critical path shifts over time.

The Importance of Critical Path

The critical path is the longest chain of linked activities that determines the earliest possible completion date. Delay analysis focuses on whether a particular event actually affected that chain. Non critical activities may suffer delay without affecting overall completion. Establishing the critical path at different points in time and demonstrating how it changed is therefore fundamental to proving or defending delay claims.

Records and Data Required for Reliable Delay Analysis

Expert analysis is only as strong as the records it relies on. Robust delay claims and defences typically require:

  • Baseline and updated programmes in native planning software format
  • Progress reports, site diaries, and meeting minutes
  • Correspondence relating to instructions, variations, and access issues
  • Daily labour, plant, and productivity records
  • Contemporaneous photos, inspection reports, and testing data

Where records are incomplete or inconsistent, experts must make assumptions and explain their limitations, which can weaken the persuasive power of their opinions.

The Role of Delay Experts

Delay experts provide independent, technical assistance to tribunals and courts. Their role is to interpret the project data, apply accepted methodologies, and present objective conclusions on responsibility for delay. Effective experts are not advocates; their primary duty is to the tribunal, not to the party instructing them. They prepare detailed reports, respond to the opposing expert, and testify at hearings where they are cross examined on methodology, assumptions, and conclusions.

Expert Reports

A typical delay expert report will describe the project, identify relevant contractual provisions, explain the chosen methodology, summarise the factual record, and present findings on the duration and cause of delays. It often includes programme graphics, narrative explanations, and sensitivity analyses exploring alternative scenarios.

Joint Expert Meetings and Statements

Many tribunals require delay experts to meet, identify points of agreement and disagreement, and produce a joint statement. This process narrows the issues and helps the tribunal focus on genuinely disputed technical points.

Concurrent Delay and Apportionment

Concurrent delay arises when two or more delay events affecting the critical path occur over the same period and are attributable to different parties. Treatment of concurrency varies by contract and governing law. Some approaches prevent the contractor from recovering additional time or cost where it also contributed to delay, while others allow time but not cost, or require apportionment. Delay experts must carefully identify overlapping events and explain how they influenced the critical path, as concurrency can significantly affect extension of time and liquidated damages positions.

Interaction Between Delay Analysis and Quantum

Delay findings often feed directly into quantum calculations. Extensions of time may reduce or eliminate liquidated damages, while established periods of employer risk delay can justify prolongation costs. Conversely, findings that place delay responsibility on the contractor may increase its financial exposure. Collaboration between delay and quantum experts is therefore essential to ensure that time and cost analyses are consistent.

Challenges and Pitfalls in Delay Expert Evidence

Tribunals frequently encounter problems such as experts acting as advocates, inconsistent use of methodologies, selective reliance on records, or failure to consider alternative scenarios. Overly complex analyses that are not clearly explained can also lose credibility. Parties should expect tribunals to scrutinise whether the chosen methodology fits the project, whether it reflects contemporaneous management decisions, and whether it is applied consistently.

Best Practices for Parties Using Delay Experts

To maximise the value of expert evidence, parties should engage delay experts early, preserve native programmes and project data, provide full access to contemporaneous records, and align the legal case theory with the technical analysis. Clear instructions that emphasise independence and integrity, rather than advocacy, will strengthen the expert’s credibility. During the dispute, parties should also ensure that their factual witnesses and expert testimony are coherent so that programme evidence aligns with lived project experience.

Conclusion

Delay analysis and expert evidence are central to resolving time related disputes in construction and infrastructure projects. By combining reliable project records, recognised analytical methodologies, and independent expert opinion, parties and tribunals can reach informed, defensible conclusions on responsibility for delay and entitlement to extensions of time or damages. Well prepared delay evidence not only strengthens a party’s position in arbitration or litigation but also supports more informed settlement discussions, helping to resolve complex disputes in a structured and technically grounded way.

Need to know more? Better ask Handle