The Dubai Court of First Instance has terminated a 25-year land investment agreement in Umm Ramool, ordered the investor to vacate and restore the plot, and awarded the landowner AED 700,000. The judgment turned on unmet obligations during a rent-free year and works carried out without permits.
What happened
The agreement originally gave the investor a 15-year term plus one rent-free year to complete construction and maintenance works on an existing warehouse, at AED 1 million a year. An amendment extended the term to 25 years and cut the annual fee to AED 700,000, leaving the other obligations unchanged. The landowner also gave the investor’s owner a general power of attorney to deal with government departments, including the Dubai Land Department.
The warehouse was fitted out and run as a self-storage facility. The landowner revoked the power of attorney by legal notice, obtained an urgent court inspection, and later served a second notice of termination. The court-appointed engineering expert found works carried out without permits or approved plans, and a permitted plan to split the warehouse into three units that was never carried out. The investor could not show when the agreed works were completed.
The court rejected the landowner’s argument that the agreement was void for not being registered in Dubai’s Interim Property Register: following Court of Cassation rulings, that requirement applies to off-plan and incomplete property, not to a vacant plot without a development project. But it held that the investor’s breaches justified judicial termination, stressing good faith and the notice served. Because the rent exemption was conditional on the works, the court awarded AED 700,000, one year’s fee under the amended agreement, rather than the AED 1,000,100 claimed, plus court fees.
What it means
- A rent-free period tied to works is a condition. If the works are not proven, the exemption can fall away.
- Records decide these cases. The investor lost largely because it could not evidence its works or their timing.
- Permits are part of performance. Works without approvals count against the party carrying them out.
- Formal notices and an early court inspection built the landowner’s case.
What to do now
- Landowners: define milestones, evidence requirements and permits in the agreement, and keep the right to inspect.
- Investors: keep completion certificates, approved plans and dated records for every works stage.
- Both: limit powers of attorney to the purpose of the agreement.
Handle’s Legal & Regulatory practice acts in property and investment disputes before the Dubai courts. See Handle Real Estate Disputes.
Source: Gulf News, 23 November 2026.