Construction disputes in the UAE are decided by the contract, the notices served under it and the expert evidence. Most large projects use FIDIC-based contracts, which sit on top of the Civil Transactions Law. This guide covers the common claims, the procedure and the steps that protect a party’s position while the project is still running.
At a glance
| Governing law | Civil Transactions Law (contracting, or muqawala, provisions), plus the contract terms |
| Typical contracts | FIDIC Red, Yellow and Silver Books (1999 and 2017 editions), with project-specific amendments; government standard forms |
| Forums | Arbitration (most large projects), onshore courts, DIFC and ADGM Courts |
| Decisive evidence | Notices, programmes, site records, correspondence and delay and quantum expert reports |
1. Common claims
- Delay and extension of time, and the related claims for prolongation costs and liquidated damages. See Liquidated damages v penalties.
- Variations: instructed changes to scope, quantities or design, and their valuation. See Claims for variations and scope changes.
- Payment: unpaid interim payment certificates, withheld retention and final account disputes. See Payment certification disputes.
- Defects: defects during the defects notification period and latent defects after handover. See Defects liability and snagging disputes.
- Termination and suspension by either party. See Suspension and termination of contracts.
- Bonds and guarantees: calls on performance bonds and advance payment guarantees, and attempts to stop them. See Performance bond and guarantee litigation.
- Force majeure and change in law. See Force majeure in construction contracts.
2. What UAE law adds to the contract
- Decennial liability. The contractor and the architect are jointly liable for the total or partial collapse of buildings and structures, and for defects that threaten their stability, for ten years from handover. Parties cannot contract out of it.
- Adjustment of liquidated damages. The court or tribunal can adjust pre-agreed damages so that they match the actual loss, on the application of either party.
- Good faith. Contracts must be performed in good faith. Strict reliance on a time bar or a termination right can be tested against it.
- Exceptional circumstances. Where unforeseeable general events make performance excessively onerous, the obligation can be reduced to a reasonable level.
3. Notices and time bars
FIDIC contracts require a party to give notice of a claim within a fixed period after it became aware of the event (28 days in the standard forms), followed by a fully detailed claim. Missing a notice can lose the claim under the contract. Whether a UAE court or tribunal will apply a time bar strictly depends on the wording, the conduct of the parties and the good faith principle, so the safe course is to serve every notice on time and keep the records that support it.
4. How a dispute runs
- Contract procedure. Engineer’s determination, then the dispute board (DAB or DAAB) where the contract provides one. See Adjudication in construction law.
- Amicable settlement period under the contract.
- Arbitration or court. Most large projects refer disputes to DIAC, arbitrateAD or ICC arbitration. Onshore courts hear smaller disputes and disputes where there is no arbitration clause. See Arbitration in the UAE.
- Experts. Delay analysis and quantum are decided by expert evidence. In onshore courts, a court-appointed engineering expert reviews the records and reports to the court.
For EPC and energy projects, see EPC contract dispute strategy.
5. While the project is running
- Keep contemporaneous records: daily site diaries, progress photos, updated programmes and minutes of meetings.
- Serve notices in the form and to the address the contract requires.
- Keep the programme updated so that delay can be analysed against it.
- Track bond expiry dates and extension requests.
- Value variations as they arise rather than at final account.
Common questions
Can an employer call a performance bond without proving loss?
An on-demand bond is payable on a compliant demand. Stopping a call generally requires showing fraud or a clear abuse, which courts treat as a high threshold.
Can a contractor stop work if it is not paid?
FIDIC contracts give the contractor a right to suspend or slow work after notice when payment is not made. Suspending without following the contract procedure risks a termination claim.
How long does a construction arbitration take?
Large construction arbitrations with delay and quantum experts commonly take one to two years from the request to the award.
Guides in this area
- Claims for Variations & Scope Changes
- Force Majeure in Construction Contracts
- Liquidated Damages vs Penalties
- Performance Bond & Guarantee Litigation
Last reviewed November 2026. This guide explains UAE law in general terms. It is not legal advice on any specific matter.
Construction claims decided by notices, records and expert evidence. Handle’s Legal & Regulatory practice runs claims positioning during the project, and arbitration and enforcement after it. Request an Initial Review.